Event power planning

Event load lists: nameplate data and operating scenarios

A load list makes a power request specific and exposes missing information before load-in. Keep nameplate ratings, planned operation and estimates in separate fields.

Use one row per device or group of identical devices

Compare scenarios with visible assumptions

Separate setup, rehearsal and show operation, and retain the manufacturer’s maximum input rating. Typical consumption helps describe operation but does not replace the maximum or justify smaller protective devices.

Watts alone do not establish AC current: voltage and power factor are also needed. Group comparable values and request review for three-phase supplies or incomplete data.

Adding loads: four fictional devices at the same voltage
AssumptionPlanned operationDeclared maximum
4 units; each has 300 W typical and 500 W maximum input4 × 300 W = 1,200 W4 × 500 W = 2,000 W
Information still neededInput current and startup dataSupply capacity to be reviewed

Ask the venue about alternatives

Compare documented existing circuits with temporary distribution coordinated by the authorized provider. Send the load-list revision, equipment locations and schedule. A nearby outlet does not establish spare capacity. Do not open panels to complete the list.

Planning questions

Is an amplifier’s output wattage its power draw?

Output power is different from mains input. Use the exact model’s electrical ratings and the manufacturer’s stated operating conditions.

Can I total only typical LED consumption?

Record maximum input ratings, planned content and brightness, and startup data. The provider can then review which scenario places the greatest demand on the supply.

Can I inquire before the list is final?

Yes. Send approximate quantities, areas and confirmed equipment. Identify alternatives and unknowns so the proposal can evolve without treating estimates as final ratings.

Sources and scope

Technical reference documentation. Venue staff and a qualified professional review its application to the actual installation.

Before finalizing the supply, confirm venue and local authority requirements in the United States, or utility and local requirements for an event in Argentina. Confirm the actual site’s electrical configuration regardless of this guide’s language.