Suspended lighting grid: points, loads and lifting plan
Review the complete load path from each fixture to the venue structure.
Define lifting and final suspension
Ask GLMedia about rental options for your event. The proposal is subject to availability, confirmation of the model and configuration, and the venue’s technical requirements.
Identify the truss system, venue points, hoists, controls and rigging hardware. Separate the lifting operation from the final suspended condition; a point approved for static suspension is not automatically a lifting point.
Venue-point limits and hoist classification
- Venue points
- Use the documented capacity of the complete point and its permitted force directions, rather than an isolated fitting rating.
- Hoist classification
- A D8+ label or double brake alone does not approve the complete overhead system.
A competent rigging team and structural designer must review the actual configuration. Manufacturer limits, local requirements and venue policy apply together.
Rigging plot and complete load schedule
Prepare a rigging plot with identified points, trim heights, truss orientation, equipment and cable weights, load positions and calculated reactions. Document hoists, controls, attachments, inspections and the agreed retention arrangement.
Checks before the planned lift
- Obtain venue authorization and verify actual point identities against the approved plot.
- Resolve load distribution and lifting conditions with the responsible designer; do not divide total weight by the number of motors.
- Agree supervision, communication, exclusion zones and emergency actions before work. Review every change before lifting.
Three technical questions
The eyebolt rating is higher than the venue point limit. Which applies?
Use the documented limit of the complete venue point for the intended direction and use. Refer any discrepancy to the venue before rigging.
Obtain the point identification, permitted force directions and any simultaneous-load restrictions from the venue. Match those records to the actual points and plot. Independent point limits must not be added to infer permission for a combined load pattern.
Can another motor make the loads equal automatically?
No. Adding a support changes load distribution. Obtain calculations and the verification method required by the approved design.
Does D8+ mean no other retention or review is required?
No. Review the complete system, intended operation, people below and venue requirements. Do not remove an agreed retention measure based only on the hoist label.
Limits before installation
Do not use a general beam table as approval for a grid or multipoint structure. NRAG guidance is contextual guidance, not confirmation of local legal compliance.
Technical guidance and manufacturer scope
Preparing a conference rigging inquiry
Start with the date, room, event purpose and an approximate idea of what needs to be suspended. If drawings or exact models are not available yet, identify the missing information: we can organize options and the scope to quote before the design is finalized.
To compare a flown grid with a floor-supported solution, we collect venue and production information. A floor-supported option also needs its footprint, floor conditions, audience access and system documentation reviewed; the absence of ceiling points does not automatically approve that option.
- Ask the venue technical contact for the current drawing, authorized point identification, load criteria and the person who receives and approves submissions. A ceiling photo can guide the inquiry but does not establish points or capacities.
- Provide approximate clear height, obstructions and restricted areas. Separate the desired equipment height from point locations and the space needed for installation.
- Collect load-in, installation and load-out windows, access routes and restrictions on lifting or suppliers. Confirm which tasks require venue staff and which production may undertake.
- Agree on deliverables: the venue supplies conditions and authorizations; production supplies documented equipment, positions and loads; competent review checks the design and its acceptance. Identify the revision, owner and open items for each document.
What can I send before the hotel provides a drawing?
Send the room name, technical contact, date, intended use and available dimensions or photos. We can prepare initial questions and options. Outstanding point and venue information remains listed for verification before installation.
Does the quote include venue approval?
The scope must be agreed: we can assess equipment supply, coordination, installation or operation according to the need. Engineering review, signed documentation and venue approval are identified as specific deliverables and responsibilities; renting equipment does not automatically include them.
What if the room or screen location changes?
Record the change in the drawing and equipment list with a date and revision, and submit it to those reviewing the points and installation. A change in position, route or work window may require a design or method review even when the total weight is unchanged.
Preparing sling, shackle and edge-protection selection
To quote accessories, link each connection to the rigging sketch. Start with readable label and marking photos, purpose and approximate dimensions; final selection requires the actual components and configuration. We do not assign capacity from color, apparent diameter or resemblance to another part.
- List each location: sling manufacturer and reference, identification, length, material, marked capacity and matching document; for a shackle, identify the body, original pin and closure system. Keep certificates and history linked to the pieces.
- Draw what each connection joins and where it contacts edges or surfaces. Record the route, geometry, intended angles and movement so competent review can determine the configuration and protection from applicable documents. A sleeve alone does not demonstrate adequate edge protection.
- Isolate pieces with uncertain identity or condition and record findings before proposing replacements. The offer can separate hardware, specified protection, inspection and assistance; every substitution must be checked against the assembly again.
Will a larger shackle work if the specified one is missing?
Comparing marked loads is insufficient. Confirm reference, pin, contact dimensions, orientation and function at that connection. We can investigate a documented alternative; a similar pin does not replace the original.
Do a product certificate and photo release a used sling for use?
They help identify it but do not establish its current condition or suitability for the assembly. Link identification, history, findings and applicable inspection. An inquiry can proceed with missing information listed without authorizing use of that piece.
CM Prostar: information for assessing the hoist and assembly
Start a Prostar inquiry with the date, venue, task and approximate travel. Specifying equipment and scope requires matching its variant and accessories; the family name does not identify a unit’s voltage, control or capacity. The CM Prostar manual P/N 192045152 Rev AB (August 2019) prohibits using the hoist to lift, support or transport people and lifting loads over people; it requires everyone to remain clear of the supported load.
- Collect a readable nameplate, model and serial number, capacity with units, supply and controller reference. The identified official manual is P/N 192045152 Rev AB, August 2019: confirm applicability to the unit before using it as a procedure.
- Separate transport receipt, installation and inspection: record shipping or equipment damage and available documents. No shipping damage does not establish current operational inspection.
- Include chain and travel, container and attachment, hooks and accessories in the assembly list. We can assess supply, installation or operation as agreed; the responsible team must resolve documentation and use conditions before work.
Can we select another Prostar simply because it is equally compact?
No. Compare nameplate, configuration and documentation with the task. Connector photos aid identification but do not establish compatible control or supply.
Does delivery of the hoist include inspection of the installation?
These are different scopes. Agree who documents the unit’s condition and inspection, who installs it and who reviews the structure, connections and operation. A hoist record does not approve all the rigging.
Help us improve this guide
Is an explanation missing, did you find an error, or did you solve something differently? Tell us on WhatsApp.
WhatsApp opens with an editable draft. Review it and send it if you choose. Do not include passwords, keys or client information. Contributions are reviewed before being added to guides; they are not published automatically.